Hello
Few check points from my side
- Check in SPRO in scheduling parameter for the order type , whether you have checked the capacity check box "Generate capacity requirement"
- Check in WC in scheduling tab , the formula has been assigned and the control key assigned to routing has checked for capacity requirements.
- In project planning board , select edit -> Functions->Activate capacities
- Also , make sure that the amount of required work is specified (not the duration).It should be directly below the WC. The formula specified in WC creation /change will create capacity requirements and the work gets distributed as per the formula.
Do let us know the status of issue.
Shubham